Round Lake Basic Water Management Project

 Project Background

The current water quality condition of Round Lake is poor, and recreational activities are impaired by summer algal blooms.  The City of Eden Prairie petitioned the District to complete this project.

 

This project's goal is to dredge 3 storm water management ponds that drain into Round Lake.  All 3 ponds have filled with sediment, thus significantly decreasing their ability to remove sediment and phosphorus.  Alum and herbicide treatments will not be conducted as originally identified in the UAA.

 

Current Project Status

 

The project is complete.  The project Expense Record was finalized and provided to Managers in November.  Presented an overview of the project at the November 2011 Managers meeting.

.

Project Schedule

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

Oct-10

Nov-10

Dec-10 through Oct-11

Construction

 

Seeding

Expense Record and Maintenance Period

Close-out

 

 

 

 
 

 Status Info

June 6, 2012
Fund: Basic Water Management Fund
To view this content, JavaScript must be enabled, and you need the Adobe Flash Player.
Get Adobe Flash player

 Budget Chart Legend

   ActualCummAmount - Actual project charges accumulated to date.

   EstCummAmount - Estimated accumulation of project charges.